Construction of Hetauda-Dhalkebar-Duhabi 400kV transmission line resumes after prolonged dispute

Part of: Hetauda-Dhalkebar-Duhabi transmission line construction resumes after dispute resolution

Construction of the Hetauda-Dhalkebar-Duhabi 400kV transmission line has resumed after years of obstruction due to local dissatisfaction, compensation disputes, and land-related issues. Initiatives by Energy Minister Biraj Bhakta Shrestha helped resolve compensation concerns, allowing tower construction to proceed. The project began in 2012, with the eastern section operational for three years, but the Hetauda-Dhalkebar section faced delays.